केंद्रीय मंत्री गडकरी का आरोप, "हमारे इंफ्रास्ट्रक्चर प्रोजेक्ट को पैसे नहीं दे रहे बैंक, RBI बाधक'////मालदीव में भारत को बड़ी कामयाबी, चीन के दबाव में वापस किए जा रहे हेलीकॉप्टर वहीं रहेंगे तैनात///President Ram Nath Kovind meets leaders of Da Nang People's Committee///Campaigning for final phase of Assembly elections ends in Chhattisgarh; picks up in MP, Telangana & Mizoram///Not Having Enough High Quality Researchers A Concern: Vice President///
Home | Latest Articles | Latest Interviews |  Past Days News  | About Us | Our Group | Contact Us
Nitin Gadkari Reviews ongoing Namami Gange Projects in Uttarakhand, Jharkhand, Bihar,
Nitin Gadkari Reviews ongoing Namami Gange Projects in Uttarakhand, Jharkhand, Bihar, and West Bengal


NEW DELHI. Nitin Gadkari, Minister for Water Resources, River Development & Ganga Rejuvenation, Shipping, Road Transport & Highways carried out an extensive and in depth review yesterday, of each ongoing project under the Namami Gange Program in the states of Uttarakhand, Jharkhand, Bihar, and West Bengal. Shri U.P Singh, Secretary, WR, RD & GR, Shri Rajiv Ranjan Mishra, Director General, National Mission for Clean Ganga, officials of NMCG and the respective state governments and the contractors executing each project were present at the review. The undergoing projects of Uttar Pradesh will also be reviewed shortly.

Shri Gadkari directed all stakeholders to expedite the execution of the projects and take proactive steps to resolve bottlenecks wherever they exist. On conclusion of the review he said, “I am happy to see that work is being carried out on a war footing and the Namami Gange Program is going to be very successful. We have also issued the notification for Aviral Ganga, to ensure uninterrupted flow of water in the river. We are constructing STPs and connecting house drainage to sewer lines. Once the projects are completed we will see remarkable change in water quality. The construction of Ghats and Crematoria are also going on and we will complete them by March 2019.”

UTTARAKHAND
32 sewerage infrastructure projects (STPs) have been sanctioned in the state, which include Haridwar (4 projects), Muni Ki Reti, Tapovan, Rishikesh ( 2 projects), Devprayag, Tehri, Uttarkashi, Gangotri, Kirtinagar, Srinagar, Rudraprayag, Karnaprayag, Nandproyag, Chamoli-Gopeshwar, Joshimath, Badrinath and Dehradun. Out of these, 15 projects have been completed, 16 are in various stages of progress and one project is under tendering process. 21 Ghats and 23 Crematoria have been sanctioned, along with 1 River Front Development (RFD) project at Chandi Ghat. Out of these projects 10 Ghats and 9 Crematoria have been completed and work is going on at a fast pace on the other projects.

JHARKHAND
Two sewerage infrastructure projects have been sanctioned at Sahibganj and Rajmahal towns in the state. Both projects are in progress.
12 Ghats and two Crematoria have also been sanctioned. Out of these, three Ghats and one crematorium have been completed. Work on other project is progressing ahead of schedule.

BIHAR
21 sewerage infrastructure projects have been sanctioned in Bihar. Of these, 11 projects are at Beur, Saidpur, Karmalichak, Kankarbagh, Digha and Pahari in Patna. The other STPs have been sanctioned at Buxar, Naugachia, Barh, Sultanganj, Mokama, Hajipur, Begusarai, Bhagalpur, Sonepur and Munger. 13 STPs in Bihar are at various stages of progress. Tenders for 4 projects have been received and are under evaluation while 3 projects are under tendering and 1 project is to be tendered.

one River Front Development (RFD) project at Patna, 14 Ghats and one Crematorium have been sanctioned and are under construction. In addition, 23 ghats and 2 crematoria have been sanctioned and are currently underway.

WEST BENGAL
16 sewerage infrastructure projects have been sanctioned at Gayeshpur, Kalyani, Bhatpara, Halishahar, Barrackpore, Budge-Budge, Nabadwip, Behrampore, Jangipur, Howrah, Bally, Kamarhati, Baranagar, Kolkata ( Tolly Nullah, Garden Reach ) Maheshtala, Hoogli-Chinsurah. Out of these, the STPs at Gayeshpur, Kalyani, Bhatpara have been completed and work is in progress for Halishahar, Barrackpore and Budge-Budge projects. In addition tenders for 3 projects have been received and are under evaluation, while 5 projects are under tendering and 2 projects are to be tendered.

In addition to the STPs, 16 Ghats and 3 Crematoria projects have been sanctioned in the state and are currently under construction.

(updated on October 24th, 2018)